CSE has been trusted to perform outage work for years and years!
Last week, our dedicated team changed out a 48’ section of a Hot Blast Recuperator weighing 65,000 pounds using our 350 ton crane. Our 90 ton crane also assisted in tailing the longer section.
This was the first time that this particular section has been removed through the top of the tower. Three levels of steel and grating were cleared in order to offer access for the replacement. In addition, two 36” inlet ducts that attach to the main section were loosened and re-welded.
Check out the pictures that show the old being replaced with the new! #constructionfriday #welding #industrialmaintenance #wedoitall